# Sprint [N] — [Start Date] to [End Date]
## Sprint Goal
[One sentence: what does this sprint achieve toward the current milestone?]
## Milestone Context
- **Current Milestone**: [Name]
- **Milestone Deadline**: [Date]
- **Sprints Remaining**: [N]
## Capacity
- **Total days**: [X]
- **Buffer (20%)**: [Y days reserved for unplanned work]
- **Available**: [Z days]
## Tasks
### Must Have (Critical Path)
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria | Status |
|----|------|-------------|-----------|-------------|-------------------|--------|
| S[N]-001 | | | | None | | Not Started |
| S[N]-002 | | | | S[N]-001 | | Not Started |
### Should Have
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria | Status |
|----|------|-------------|-----------|-------------|-------------------|--------|
| S[N]-010 | | | | | | Not Started |
### Nice to Have (Cut First)
| ID | Task | Agent/Owner | Est. Days | Dependencies | Acceptance Criteria | Status |
|----|------|-------------|-----------|-------------|-------------------|--------|
| S[N]-020 | | | | | | Not Started |
## Carryover from Sprint [N-1]
| Original ID | Task | Reason for Carryover | New Estimate | Priority Change |
|------------|------|---------------------|-------------|----------------|
## Risks to This Sprint
| Risk | Probability | Impact | Mitigation | Owner |
|------|------------|--------|-----------|-------|
## External Dependencies
| Dependency | Status | Impact if Delayed | Contingency |
|-----------|--------|------------------|-------------|
## Definition of Done
- [ ] All Must Have tasks completed
- [ ] All tasks pass acceptance criteria
- [ ] QA plan exists (`production/qa/qa-plan-sprint-[N].md`)
- [ ] All Logic/Integration stories have passing unit/integration tests
- [ ] Smoke check passed (`/smoke-check sprint`)
- [ ] QA sign-off report: APPROVED or APPROVED WITH CONDITIONS (`/team-qa sprint`)
- [ ] No S1 or S2 bugs in delivered features
- [ ] Design documents updated for any deviations
- [ ] Code reviewed and merged